Building the infrastructure for Liverpool’s next waterfront neighbourhood
A year into construction, significant progress is being made on the £81m Central Docks infrastructure project, part of the wider Liverpool Waters regeneration.
We're proud to be lead design consultant, appointed by GRAHAM to lead the detailed design and delivery of the infrastructure that will unlock this major new neighbourhood in Liverpool's historic northern docklands, within the city's UNESCO World Heritage setting.
Working alongside Homes England, Peel Waters and Liverpool City Council, the project will prepare the site for 2,350 new homes, alongside public spaces, green infrastructure and improved connections across the waterfront.
Laying the foundations for future development
The infrastructure works are progressing across the site, with GRAHAM now a year into construction. Work includes:
- 12 miles of utility ducting
- 1.7 miles of drainage systems
- New highways infrastructure
- Foundations for two new bridges across the canal
- A new 4.7-acre Central Park
The infrastructure is expected to be completed in 2028, creating development-ready plots and the framework for a new waterfront community.
Building on our earlier work supporting the emerging masterplan, Civic was appointed by GRAHAM as lead design consultant for the detailed design and delivery of the site's remediation and infrastructure.
Our teams are working across several key elements of the project:
Civil engineering
Our civil team has worked on the design of Central Park, a new 4.7-acre green space at the heart of the neighbourhood. Designed to provide a place for people to meet, play and enjoy nature, the park will include new trees, children's play areas, a community garden and open parkland.
Transport and movement
Our transport and movement team has worked closely with Peel Waters, alongside appointed architect and landscape architect Planit, to help guide the wider masterplan. This includes ensuring individual development plots align with the overarching strategies for active travel, connectivity, vehicular access and parking.
The wider proposals also include around 8km of people-focused streets, prioritising walking, wheeling and cycling, alongside improved connections to the surrounding waterfront.
Structures
Our structures team has designed a new road bridge and the abutments and foundations for a separate pedestrian bridge. The team has also contributed to several features across the public realm, including a covered outdoor performance space, foundations for an artist-designed feature pergola, a new kiosk and viewing platforms along the waterfront and canal.
Earth and environment
Our earth & environment team has provided comprehensive geotechnical services, including site history characterisation, on-site support and contamination risk assessments. This work is helping inform the remediation and development of the previously infilled dockland alongside the existing canal.
Together, these contributions are helping transform a complex brownfield site into a connected, accessible and climate-resilient neighbourhood.
Key team
Services